Subject: (Item A-2) Resolution 2020-49 Award of Contract and Authorization to Begin Work for the Kitchen Renovation at Houston/Serna Project No. 0803-8103 (Mr. Kahn)
:
Enclosure: Resolution 2020-49
File Attachment:
Resolution 2020-49 Award of Contract Houston-Serna Kitchen Renovation.ada.pdf
Summary: On May 21, 2020, the District received five (5) bids. The lowest bidder was F&H Construction of Lodi, California, in the amount of $1,256,000.00. Approval of this Resolution certifies the Award of Contract to F&H Construction. The total amount to be budgeted is $1,356,000.00, which includes a $100,000.00 District controlled construction allowance.
Funding: This project will be funded by Fund 40.
Recommendation: It is recommended the Board of Education adopt Resolution 2020-49.